Riccardo Arseni

Control System Specialist

PROJECTS

Here below indicated projects where i had been involved

Latest Projects

 

      2018 (May)

      Rashid Offshore plant – Dubai (Dubai Petroleum)

      For BHGE Oil&Gas Commissioning of 2 Superior units type HSR MH64 (PLC Allen Bradley) driven by Waukesha Engine VHP-L7044LT

      (12 cylinders).

 

      2018 (March/April)

      AFAM III – Nigeria

      For BHGE Oil&Gas Pre Commissioning of one Ajax Unit Type DPC-2804LE (PLC GE Fanuc – CPU RX3i) and 3 Superior units type

      HSR MH62 (PLC Ge Fanuc – CPU RX3i) driven by Waukesha Engine VHP-L5774LT (12 cylinders).

 

      2017 (October/November)

      Agiba Station – Meleiha (Egypt)

      Service in Melehia Gas Plant as BHGE representative. Installed and configured APM – Ge Digital (asset performance management)

      module in order that end user can check compressors data from a webserver.

 

      2017 (July/August)

      Khazzan Project – Petrofac / BP(Oman)

      Yokogawa SIS DCS - Commissioning and Start up for BHGE Oil&Gas – 2 Units type WG64 (2 stages) driven by ABB electrical motor

      and 2 units type RAM54 (2 stages) driven by ABB electrical motor.

 

      2016 (May / November)

      Sarmasel - Romgaz (Romania)

      Pre-Commissionig, Commissioning and Start up for GE Oil&Gas Dowstream technology .

      4 Superior Units WH74 driven by Waukesha Gas Engine 12 cylinders.

 

      2015 (July) / 2017 (January)

      Meleiha - Agiba (Egypt)

      Pre-Commissionig, Commissioning and Start up for GE Oil&Gas Dowstream technology .

      2 units WG76 4 stages Superior Compressors driven by Waukesha Gas Engine 16 cylinders

      4 Ajax units

 

      2015 (November)

      Poltava – Plast (Ukraine) - JSPC Plast company

      Commissioning and Start up for GE Oil&Gas Dowstream technology.

      1 Ajax unit

 

      2015 (January/April)

      Bashra – WQ2 (Iraq) - Lukoil Overseas

      AC800M (ABB) - Maintenance and software implementations

 

      2014 (May/October)

      Urziceni – RomGaz (Romania)

      Commissioning and Start up for Ge Oil & Gas Downstream technology. Modified all the sequence logics according with customer

      request and Start up for 4 compressors WG64 (2 stage).

 

      2014 (March/July)

      Bashra – WQ2 (Iraq) - Lukoil Overseas

      AC800M (ABB) Pre-Commissionig, Commissioning and Start up for Cameron Compressors  MH64 driven by ABB Electrical motor

      BENTLY NEVADA ( SYSTEM1) Server configuration, Pre-Commissionig, Commissioning and Start up for Cameron Compressors

      West urna 2

 

      2014 (February)

      Urga (Uzbekistan) - Erriel

      Siemens S7-400 Start-up for Cameron Compressors

 

      2013 (November)

      Molve (Croatia) - INA

      AC800M (ABB) Pre-Commissionig for Cameron Compressors

 

 

Previous Projects

 

      Icatec Srl

      2013

      Sinopec (Luntai  - China)

      Installation, pre-commissioning, Commissioning and Start up of Cameron superior WG76 Compressor Driven by Caterpillar Engine–

      Allen Bradley PLC - Redlion HMI

 

      2012

      Lorestan Petrochemical (Iran)

      Engineering, logics, network, graphics and FAT for Rhine plant – Fire & gas failsafe system with PLC S7 400

 

 

      2011

      Ava (Schio – Italy)

      Logics implementation, Graphic page, commissioning and Start Up of Termovalorizzatore – DCS AC800F (Control Builder F + Tenore)

 

 

      Emerson Process Management

      2010-2011

      SEF - Ferrara:

      Development of the logic and SCADA pages, commissioning and tuning; Switch DMZ implementation of access rules ( Ovation

      Emerson Process Management – Italy ).

 

      C&T - Termoli & Airasca:

      Expediting and SAT c/o C&T Termoli and Airasca plant (Ovation ; Emerson Process Management – Italy )

 

      TME - San Vittore del Lazio:

      Logic Development and tests; SAT (Ovation ; Emerson Process Management – Italy )

 

      Italcementi – Salerno:

      Downgrade of a new local station added on the local network. It’s actually used in the control room as Operator Station ( Ovation

      Emerson Process Management – Italy).

 

      Edison – Bussi :

      F.A.T. c/o  EDISON BUSSI on DCS Ovation SIS (Safety Instrument Solver) – (Ovation Emerson Process Management – Italy).

 

      Telvent – Sevilla:

      Expediting and SAT c/o Telvent (Schneider Electric PLC – Italy )

 

       Advanced Control Systems srl

      2007-2010

      Fired Heater 40H-1 Suez Egypt:

      Software engineer. SCADA pages and commissioning ( DeltaV Emerson Process Management – Italy ).

 

      Q8 Fuel Depot DCS Revamping - Napoli :

      Development of the logic and SCADA pages, commissioning ( DeltaV Emerson Process Management – Italy ).

 

      Polimeri Europa P1CR – Brindisi:

      Signals migration from old termination NTU7C4 to new terminations NTU7C7, Development of the logics and SCADA pages

      (ABB INFI90)

 

      Polimeri Europa GPL Plant – Brindisi:

      SCADA pages and SCSI communication configuration between node DELTAV and node INFI90

      (DeltaV Connect Emerson Process Management – Italy)

 

      Polimeri Europa P30B Plant – Brindisi:

      SCADA pages and SCSI communication configuration between node DELTAV and node INFI90

      (DeltaV Connect Emerson Process Management – Italy)

 

      Fired Heater – Suez Egypt

      SCADA pages, logic development, tests on DCS Yokogawa Millenium CS3000

 

      R116-H1 – Iran

      Logic implementation, F.A.T and S.A.T. on a PLC HIMA (BMS)

 

      Polimeri Europa P39 Plant – Brindisi:

      Maintenance and signals implementation on Deltav ( Emerson Process Management – Italy)

 

      Polimeri Europa Biologico Plant – Brindisi:

      Maintenance and signals implementation on Deltav ( Emerson Process Management – Italy)

 

 

Powered by Riccardo ARSENI

Rev. 2